Generating power and controversy: Understanding Tanzania’s independent power projects
DOI:
https://doi.org/10.17159/2413-3051/2006/v17i4a3205Keywords:
Tanzania, independent power projects, power sector reform, power purchase agreements, Tanzania Electric Supply Company LimitedAbstract
Initially conceived of within the broader context of power sector reform in the late 1980s and early 1990s, Independent Power Projects (IPPs) were intended to relieve state utilities of the burden of financing new plants, bring quick, quality power and reduce costs for end-users. Although IPPs have indeed contributed to generation capacity in Tanzania, much of the power that resulted from investments has been supplied neither quickly nor cheaply. Embarking on power sector reform in the early 1990s, Tanzania made IPPs a pillar of its reform strategy. Presently, Songas and IPTL, the country’s two IPPs are helping to reduce load shedding. However, these projects have not been without controversy. One of Tanzania’s IPPs was taken to international arbitration over a dispute related to construction costs. The state electric utility, Tanzania Electric Supply Company Limited (TANESCO), currently pays more than 50% of its current revenue towards combined fuel and capacity charges for the IPPs. Capacity charges for the country’s two IPPs are equivalent to approximately one percent of GDP. The Government of Tanzania (GoT) is intervening to assist TANESCO with its monthly IPP payments at present. With twenty-year Power Purchase Agreements (PPAs) between IPPs and TANESCO, these costs are expected to continue, albeit with some modifications due to refinancing, fuel conversion and further development of the natural gas market. This paper provides a detailed summary of how and why IPPs developed in Tanzania as well as their impact to date. Development outcomes, namely the extent to which the host country is benefiting from reliable, affordable power and investment outcomes, the degree to which investors have made favourable returns and been able to expand market share, are analysed in turn. IPPs offer more than a decade of experiences in private sector investment in developing countries and a detailed understanding of them may be the key to unlocking and sustaining future power investment.Downloads
References
Africa Electra, 2006. ‘EAST: Investors eye short-term
power potential in drought’, Issue 41.
Africa Electra, 2005. ‘Tanzania’, Issue 34.
All Africa, 2001. ‘Gas Project Attracts US$183m from
World Bank’, 22 October.
All Africa, 2003. ‘Govt, Independent Power Ltd.
Negotiate Power Tariff Cuts’, 6 June.
All Africa, 1998. ‘IPTL Supplier Shrugs off Malaysians’
Protest’, 28 April.
Business Times, 2001,‘Mechmar expects to see US$62m
contribution from Tanzanian project’, 15 February.
Business Wire, 2001. ‘AES Tanzania Completes $250 million
Project Financing; Songo Songo Gas-to-Electricity Project under Construction’, 12 October.
Clark, A et al, 2004. ‘Power sector reform in Africa:
assessing the impact on poor people’, ESMAP/The
World Bank, Washington D.C., October.
Davies, I 2004. Management Contracts in the Electricity
Sector: A Case Study-Tanzania.
Campbell Davies Consulting.
Economist Intelligence Unit, 2004. ‘Energy & Electricity:
Tanzania’, 16 July.
Economist Intelligence Unit, 2003. ‘Tanzania: Energy
Provision’, 24 November.
ESMAP 1998. ‘ Tanzania Power Loss Reduction Study’.
Volume 1 and 2. Report No. 204A/98. Washington
DC, Energy Sector Management Assistance Program,
World Bank.
Ferreira, 2004. ‘African IPP Experience’, Conference
presentation for Independent Power Producers and
Power Purchase Agreements: Frontiers in
International Experience, May 3, 2004.
Hosier, R. H. and W. Kipondya 1993. ‘Urban household
energy use in Tanzania’, Energy Policy 21(5): 454-
ICSID 2001. ‘Tanzania Electric Supply Company Limited
v. Independent Power Tanzania Limited’, Case No.
ARB/98/8, Washington DC, International Centre for
Settlement of Investment Disputes.
Katyega, M. 2004. ‘Outsourcing Opportunities for Small
and Medium Enterprises in the Ongoing Utility
Reforms in Tanzania’, ESMAP/AFREPREN Report.
Liquid Africa, 2004. ‘Investment by FMO Broadens
Ownership of Tanzanian Power Project’, 17 February.
Liquid Africa, 2004. ‘Songas to Replace Imported
Furnace Oil’, 15 July.
Marandu, E 2002. ‘The Prospects for local private investment in Tanzania’s rural electrification. Energy Policy,
: 977-985.
MEM 1992. ‘The Energy Policy of Tanzania’. Dar es
Salaam, United Republic of Tanzania, Ministry of
Energy and Minerals.
MEM 2003. ‘Proposal for Establishment of a Rural
Energy Agency (rEA) and a Rural Energy Fund
(REF)’, Dar es Salaam, United Republic of Tanzania,
Ministry of Energy and Minerals.
MIR 2005. The Experience of IPPs in Africa: an overview,
working paper, Management
Programme in Infrastructure Reform & Regulation,
Graduate School of Business, University of Cape
Town.
Mokhtar, N 1998. ‘Mechmar’s IPP to be single largest
contributor’, The Sun, 17 June.
Mwandosya, M. J. and M. L. Luhanga 1993. ‘Energy and
development in Tanzania: Issues and perspectives’.
Energy Policy May: 441-453.
The Oil and Gas Journal, 2001. ‘Tanzania’, 5 November.
Power Economist, 1998. ‘Power Contract-Tanzania renegotiates
with Malaysian IPP’, 30 June.
Reuters News, 2001. ‘Tanzania says power plant to start
production’, 26 July.
SAD-ELEC 2004, Reform and Restructuring of the
Electricity Supply Industry Status Report. SAD-ELEC,
Rivonia, South Africa.
Sakran, S 2002. ‘Turning off the power’, Malaysian
Business, 1 April.
Shirima, H 2002. ‘Power Sector Reforms and Regulation
in Selected Eastern and Southern Africa Countries.’
Unpublished Masters Thesis for University of Cape
Town Energy and Development Research Centre.
TANESCO 1995. ‘Power Purchase Agreement between
Independent Power Tanzania Limited and Tanzania
Electric Supply Company Limited’.
TANESCO 2004. ‘Amended and Restated Power
Purchase Agreement, Tanzania Limited and Tanzania
Electric Supply Company Limited and Songas
Limited’, Dar es Salaam, Tanzania.
TANESCO 2004. ‘Amended and Restated Shareholders’
Agreement, Relating to the Songo Songo Gas-toElectricity
Project’, Dar es Salaam, Tanzania.
TANESCO 2004. ‘Annex F, Amended and Restated
Power Purchase Agreement, Tanzania Limited and
Tanzania Electric Supply Company Limited and
Songas Limited’, Dar es Salaam, Tanzania.
Turner, M 1998. ‘Tanzania submits power dispute to arbitration,’
Financial Times, 2 December.
Victor, D et al 2004. ‘The Experience with Independent
Power Projects (IPPs) in Developing Countries:
Introduction and Case Study Methods’, Working
Paper #23. Retrieved November 20, 2004 from
http://pesd.stanford.edu/publications/20528/.
Wangwe, S., H. Semboja, et al. 1998. ‘Transitional
Economic Policy and Policy Options in Tanzania’,
Tanzania Political Economy Series 1. Dar es Salaam,
Tanzania, Economic and Social Research
Foundation.
World Bank 1993. The World Bank’s Role in the Electric
Power Sector. Washington, DC, World Bank.
World Bank 2001. International Centre for Settlement of
Investment Disputes Case No. ARB/98/8. Washington
DC: World Bank.
World Bank 2001. Project Appraisal Document: On a
proposed credit to the United Republic of Tanzania
for a Songo Songo gas development and power generation
project. Report No: 21316-TA. Washington
DC: World Bank.
World Bank 2004. Private Participation in Infrastructure
Database, http://ppi.worldbank.org.
World Gas Intelligence, 2001. ‘Trials and Tribulations of
West Africa Gas-to-Power Deals’, 11 July.